2016 Liberty-Eylau ISD Bond Update
On May 7, 2016 the Liberty-Eylau Community voted in favor of 2 bond measures. Proposal 1 totals $19.9 Million for upgrading campuses and buildings. Proposal 2 totals $985,000 for upgrading Harris Field. This page will be used to update the public on the status of the bond projects. Here we will share construction photos and videos as well as project schedules.
CLICK HERE FOR THE MOST RECENT PROJECT UPDATE
FOR PHASE 1 FINAL COSTS CLICK HERE
Below is the anticipated schedule for 2016 BOND Program:
Summer 2016- Purchase land adjacent to the Primary school -DONE
Install a new middle school roof -DONE
Install turf on Harris field, resurface the track, renovate concession stands and build restrooms -DONE
Oct 2016-Accept a guaranteed maximum price for PRE-K and CTE projects and begin construction on those two projects. -DONE
Jan 2017- Accept a guaranteed maximum price for the new Elementary on HWY 59. (Site construction begins)
June 2017- New Elementary building construction begins -IN PROGRESS
August-2017- Pre-K and Kindergarten will begin school at Grandview Campus
Grades 1-4 will begin school at CK Bender Campus -DONE
August 2018 - Grades 1-4 moves to new Elementary Campus
**Please note these dates are estimates based on cooperating weather and building conditions**