2016 Bond Election Information

2016 Liberty-Eylau ISD Bond Update

 

On May 7, 2016 the Liberty-Eylau Community voted in favor of 2 bond measures. Proposal 1 totals $19.9 Million for upgrading campuses and buildings. Proposal 2 totals $985,000 for upgrading Harris Field. This page will be used to update the public on the status of the bond projects. Here we will share construction photos and videos as well as project schedules.

CLICK HERE FOR THE MOST RECENT PROJECT UPDATE

FOR PHASE 1 FINAL COSTS CLICK HERE

Below is the anticipated schedule for 2016 BOND Program:

 

Summer 2016- Purchase land adjacent to the Primary school -DONE

                          Install a new middle school roof -DONE

                          Install turf on Harris field, resurface the track, renovate concession stands and build restrooms -DONE                      

Oct 2016-Accept a guaranteed maximum price for PRE-K and CTE projects and begin construction on those two projects. -DONE

 

Jan 2017- Accept a guaranteed maximum price for the new Elementary on HWY 59. (Site construction begins)

 

June 2017- New Elementary building construction begins -IN PROGRESS

 

August-2017- Pre-K and Kindergarten will begin school at Grandview Campus 

                        Grades 1-4 will begin school at CK Bender Campus -DONE

 

August 2018 - Grades 1-4 moves to new Elementary Campus

**Please note these dates are estimates based on cooperating weather and building conditions**

 